AI Data Centers

GPU Colocation Pricing per kW: Power, Cooling and Rack Costs Explained

GPU colocation pricing varies by market, reserved power, rack density and cooling requirements. Published U.S. high-density colocation rates range from approximately $100 to $350 per kW per month, while general colocation benchmarks in major Asia-Pacific markets range from $188/kW in Sydney to $403/kW in Singapore.

A 100 kW GPU deployment at $200/kW costs $20,000 per month for reserved capacity, before any separately billed electricity, cooling or services. To calculate the actual cost, buyers must understand what the quoted rate includes and which charges are added separately.

How Much Does GPU Colocation Cost per kW?

Published rates vary by market, power availability and the density a facility can accommodate.

QuoteColo's 2026 pricing guidance provides the following U.S. high-density colocation estimates:

MarketPrice per kW/monthTypical supported rack density
North/South Dakota$100–$17020–60 kW
Washington State$110–$18020–50 kW
Pacific Northwest$120–$20015–50 kW
Phoenix$130–$22015–40 kW
Dallas$140–$24010–40 kW
Chicago$160–$26010–25 kW
Northern Virginia$180–$30010–30 kW
Silicon Valley$200–$35010–25 kW

These are indicative rates, not guaranteed quotes for every GPU configuration. Supported rack density also varies within each market.

The monthly capacity charge scales with contracted power:

Reserved power$150/kW/month$200/kW/month$250/kW/month
20 kW$3,000$4,000$5,000
50 kW$7,500$10,000$12,500
100 kW$15,000$20,000$25,000
200 kW$30,000$40,000$50,000

These calculations exclude charges not included in the quoted rate.

How Much Does GPU Colocation Cost Across Asia-Pacific?

Published colocation rates vary considerably across Asia-Pacific, although most available benchmarks cover general data center capacity rather than GPU-specific infrastructure.

CBRE's Global Data Center Trends 2026 reports the following average asking rents for 250–500 kW capacity requirements:

MarketAverage USD/kW/monthIllustrative 250 kW monthly cost
Singapore$403$100,750
Hong Kong$295$73,750
Tokyo, Japan$280$70,000
Sydney, Australia$188$47,000

Source: CBRE Research, Q1 2026. The 250 kW figures are calculated from market averages, not individual facility quotes.

Singapore is the most expensive of these four markets. CBRE reports asking rents of $330–$475/kW per month, reflecting constrained power availability and limited capacity.

India provides another pricing reference. Cushman & Wakefield's H1 2025 market report publishes the following Mumbai colocation rates:

Contracted capacityMonthly rent (INR/kW)
Below 250 kW₹8,000–₹12,000
250 kW–1 MW₹7,000–₹10,000
1–5 MW₹6,500–₹8,000
Above 5 MW₹6,000–₹7,500

The Mumbai figures assume conventional 5–7 kVA racks, while CBRE's benchmarks cover larger colocation commitments. Neither provides a confirmed rate for 40–100+ kW GPU racks.

Comparable published GPU-specific pricing for Bangkok and Johor remains limited.

These figures establish regional pricing benchmarks, but high-density GPU deployments require quotes that account for rack power, cooling infrastructure and the services included in the rate.

What Determines GPU Colocation Pricing?

Five factors explain why providers can charge different amounts for the same GPU deployment.

1. Reserved Power Capacity

Many facilities charge for committed electrical capacity rather than actual consumption alone.

For example, reserving 100 kW at $200/kW produces a $20,000 monthly charge, even when the GPUs draw less than their contracted capacity.

Buyers should confirm the minimum commitment, billing threshold and overage terms.

2. GPU Rack Density

Higher rack density can increase costs because fewer facilities can support the required power and cooling capacity.

Facilities supporting 20 kW per rack may price deployments differently from those accommodating 80 kW liquid-cooled racks. High-density GPU colocation can also require additional power distribution and cooling infrastructure.

For a 100 kW deployment, spreading equipment across five 20 kW racks instead of two 50 kW racks can change space and cooling charges.

Compare both $/kW and supported power density per rack.

3. Cooling Requirements

High-density GPU systems may require rear-door heat exchangers or direct liquid cooling, potentially adding to the monthly bill.

Published estimates place specialized cooling upgrades at $500–$2,000 per rack per month for certain deployments. Four racks with a $1,000 monthly surcharge each would add $4,000 per month, or $48,000 annually.

Some providers include cooling in the base rate, while others charge separately for specialized infrastructure or services.

4. Electricity and Facility Efficiency

Electricity affects the total cost when a provider bills consumption separately from reserved capacity.

The distinction is:

  • kW: electrical capacity reserved under the contract.
  • kWh: electricity consumed during the billing period.

Upstack's colocation pricing guide also distinguishes IT power from the energy required to support facility operations.

For example, a modeled PUE of 1.30 means 100 kWh of IT energy corresponds to 130 kWh of total facility energy under consistent measurement boundaries.

A provider may include these costs in one rate or pass them through separately. The contract determines whether and how additional facility energy is billed.

5. Location and Power Availability

Regional electricity costs, facility capacity and infrastructure constraints affect available rates.

For example, CBRE reports average colocation rents of $403/kW in Singapore and $188/kW in Sydney. These are general colocation benchmarks, not directly comparable GPU-specific quotes.

At 100 kW, a $50/kW difference between otherwise equivalent offers amounts to $5,000 per month, or $60,000 annually.

However, a lower-cost location must still meet the deployment's power, cooling, connectivity and redundancy requirements.

How Is GPU Colocation Power Billed?

Providers may charge for reserved capacity, actual electricity consumption or both.

Billing modelHow it worksCost implication
Committed kWFixed monthly capacity chargePredictable base cost
Metered kWhCharge based on electricity consumedVaries with average power draw
CombinedReserved capacity plus metered electricityFixed and variable charges
All-inclusiveDefined facility services bundled into one rateSimpler billing, subject to contract inclusions

Some leases also pass through operating expenses or facility-energy costs, while others incorporate them into the quoted rate.

The important distinction is whether electricity, cooling and operating expenses are included or charged separately.

Two providers quoting $200/kW may therefore produce different monthly bills.

What Additional Charges Should You Expect?

The advertised rate may exclude recurring and one-time services. Published high-density colocation pricing estimates identify the following indicative costs:

ChargeIndicative priceBilling basis
Cross-connects$100–$400Per connection/month
Remote hands$150–$300Per hour
Installation and turn-up$500–$3,000One time
High-density cooling upgrades$500–$2,000Per rack/month
Burst bandwidthVariesUsage or contract terms
Rack or cage spaceVariesPer rack/month or included

Not every facility bills these items separately. Some include standard space, connectivity or cooling in the monthly commitment.

For accurate colocation pricing, request an itemized quote distinguishing included services from additional fees.

How to Calculate Monthly GPU Colocation Costs

Consider a 64-GPU H100 deployment requiring an assumed 100 kW of reserved IT capacity. Actual requirements depend on the servers, networking, storage and operating configuration.

Step 1: Calculate Reserved Power

Metro Colo Advisory uses approximately $204/kW per month in its GPU ownership-and-colocation model.

Applying that rate:

100 kW × $204 = $20,400/month

Annual capacity charge:

$20,400 × 12 = $244,800

The $204 figure is a modeling assumption, not a confirmed all-inclusive facility quote.

Step 2: Add Metered Electricity, If Separate

Assume:

  • Reserved capacity: 100 kW
  • Average IT power draw: 70 kW
  • Operating period: 730 hours/month
  • Electricity rate: $0.12–$0.15/kWh

Monthly consumption:

70 kW × 730 hours = 51,100 kWh

Electricity cost:

$6,132–$7,665/month

If facility energy overhead is also passed through, a modeled PUE of 1.30 would increase total billed energy to 66,430 kWh, equivalent to $7,972–$9,965/month at those electricity rates.

These are alternative electricity calculations, not charges to add together. Neither should be added if the contracted rate already includes the relevant energy costs.

Step 3: Add Cooling and Connectivity

Assume the provider charges:

  • Two cross-connects at $200/month each: $400/month
  • Cooling upgrades for two racks at $1,000/month each: $2,000/month
  • Installation and turn-up: $1,500 one time

Recurring additional charges total $2,400/month.

This example assumes cabinet space is included in the base rate.

Step 4: Calculate the First-Year Total

ComponentMonthly recurringFirst year
Reserved 100 kW capacity$20,400$244,800
Cross-connects$400$4,800
Cooling upgrades$2,000$24,000
Installation—$1,500
Total before separate electricity$22,800$275,100

If electricity is billed separately at $6,132–$7,665 per month, with no additional facility-energy charge, the first-year estimate increases to approximately $348,684–$367,080.

The example excludes any other unquoted charges.

How to Compare GPU Colocation Quotes

The lowest advertised $/kW rate does not necessarily produce the lowest monthly cost.

Consider two hypothetical quotes for the same 100 kW deployment:

Pricing componentProvider AProvider B
Reserved power rate$150/kW$220/kW
Base monthly charge$15,000$22,000
Separately billed electricity$6,500Included
Additional cooling$2,000Included
Rack and connectivity charges$1,000$1,000
Total monthly cost$24,500$23,000

Despite its higher headline rate, Provider B costs $1,500 less per month under these assumptions.

For another deployment-level reference, Clusterbid's 128-GPU H100 example estimates $15,000–$25,000 per month for space, power and cooling. Its assumptions differ from the example above, so the figures should not be compared without reconciling actual power draw and inclusions.

The correct comparison uses equivalent reserved capacity, average consumption, cooling requirements and services.

GPU Colocation Pricing Checklist

Before accepting a quote, confirm:

  1. Power rate: What is the $/kW price, and which load measurement does it apply to?
  2. Reserved capacity: What minimum commitment and overage terms apply?
  3. Electricity: Is metered consumption included or billed separately?
  4. Rack density: Can the facility support the required kW per rack at the quoted rate?
  5. Cooling: Are high-density upgrades included?
  6. Rack space: Are cabinets, cages and floor space included?
  7. Redundancy: What power redundancy is provided, and does it affect pricing?
  8. Connectivity: What are the bandwidth, port and cross-connect charges?
  9. Installation: What one-time deployment fees apply?
  10. Contract terms: Are there minimum terms, annual escalations or utility pass-throughs?
  11. Total monthly cost: What is the recurring bill under the expected power consumption?

Compare fixed commitments separately from variable charges so that differences in operating assumptions do not distort the result.

How Much Does Colocation Cost per GPU?

The facility bill can also be expressed per installed GPU for budgeting.

Using the 64-GPU example:

$22,800 monthly recurring cost ÷ 64 GPUs = $356.25 per GPU/month

Including installation:

$275,100 first-year facility cost ÷ 64 GPUs = approximately $4,298 per GPU in year one

These amounts exclude separately metered electricity and other unquoted charges.

Cost per GPU helps with internal budgeting, but $/kW remains the more useful metric when comparing facility offers because GPU configurations have different power and cooling requirements.

What Is the Best Way to Budget for GPU Colocation?

Build the budget around the contracted power charge, then account for separately billed electricity, cooling, rack space, connectivity and installation.

Keep recurring commitments separate from variable expenses and one-time fees. This makes it easier to compare providers across markets and understand how changes in energy consumption affect the bill.

Hardware procurement and financing remain separate costs. Organizations purchasing GPUs for colocation can evaluate GPU financing independently of the facility contract.

The most useful pricing comparison is the total monthly cost of reserving, powering, cooling and connecting the same GPU deployment—not the advertised $/kW rate alone.