AI Data Centers

Leasing Colocation Space for GPU Racks: Power Commitments, Ramp Schedules, Term Length and SLAs in a GPU Colocation Lease

Match the committed power in a GPU colocation lease to each rack's delivery and switch-on date. Providers often bill committed power on take-or-pay terms, so the tenant pays for capacity reserved for racks still on order.

Introl says a GB200 NVL72 rack draws 120 kW to power 72 NVIDIA GPUs. Introl also says providers often set a utilization floor: the tenant must draw 80% of committed power within six months.

Ask the provider to start that six-month clock on each rack's switch-on date. Write that date into the term sheet, the summary of deal terms both sides agree before the contract.

Which four terms bind a GPU colocation tenant?

Four terms set the tenant's costs and the length of the commitment:

  1. Committed kW: the power reserved for each cabinet, billed at the reserved amount, including months with an empty cabinet.
  2. Delivery schedule: each rack's delivery and switch-on date, which should start the six-month clock on the utilization floor.
  3. Term: the length of the commitment in months, with the renewal and exit rules for the end date.
  4. SLA: the service level agreement, which sets uptime and cooling targets and the SLA credits paid on a missed target.

Which lease documents decide a GPU dispute?

A colocation agreement splits into three linked documents, according to 3EX Hosting's guide to colocation contracts:

  1. Master Service Agreement (MSA): the long-term legal terms, such as liability limits, renewal options and indemnification, the promise to cover the other side's losses.
  2. Service Level Agreement (SLA): the uptime targets and credit rules, plus latency, humidity and response-time targets for remote hands, the on-site technicians who work on a tenant's equipment.
  3. Service Order: the document that names the exact cabinet, its power draw in kilowatts and the monthly recurring charge.

An order-of-precedence clause decides which document wins a conflict, and 3EX says it usually ranks the Service Order or SLA above the MSA on technical details. Write committed kW into the Service Order so the per-cabinet figure outranks a general MSA clause.

How committed kW is sized and billed for a GPU rack

Before sizing the commitment, check the facility's rack density limit, the maximum power per cabinet. Introl describes traditional providers that struggle with 10 kW racks, a twelfth of a GB200 NVL72's draw.

Introl puts the penalty for drawing above the commitment at $500 to $1,000 per kW. Seven terms change the monthly bill, so get each one written as a number:

  1. Committed kW per cabinet: the Service Order figure for each cabinet, set at its rack's peak draw, with the lease commitment equal to the sum of these figures.
  2. Billing on committed draw: the kW figure the charge applies to, how often the provider meters draw, and the excess-usage penalty per kW.
  3. Utilization floor and its deadline: the percentage, the date measurement starts and the test date, with the start tied to each rack's switch-on date.
  4. Release of unused power: Introl says providers treat allocated power as non-reclaimable, so name the events that release kW from a cancelled or delayed rack, and the release date.
  5. Growth reservation: future capacity held at today's price, with the kW amount and an expiry date for the reservation.
  6. Metered or fixed-fee billing: the bill each model produces below the floor, since 3EX says metered billing usually suits AI workloads better than a fixed fee.
  7. Circuit and phase specification: the circuits, amperage and phase per cabinet in the Service Order, because Introl says a 120 kW rack needs 600 amps at 208 V three-phase.

Matching committed kW to GPU rack delivery

Take a hypothetical lease for ten GB200 NVL72 racks at 120 kW each, which commits 1,200 kW. An 80% utilization floor on that commitment comes to 960 kW.

Six running racks draw 720 kW at peak by the six-month deadline, 60% of the commitment. The tenant misses the floor by 240 kW and pays for four racks still on the way.

Large cloud companies already tie rent to power delivery, and Peony's data room guide says rent in their building leases often rises with each block of delivered power.

A utility states its intent to power a site in a will-serve letter, and Peony says that letter doesn't fix a delivery date.

The provider's power date can slip with the utility's, so ask the provider to commit to power and space on stated dates, with a remedy for each missed date. A floor clock that starts at signing makes the tenant pay for delivery delays.

Lease term length, renewal, expansion and exit

Match the initial term to the GPU refresh cycle, because 3EX says GPU generations often need power and connectivity upgrades on a 24- to 36-month cycle. Peony says leases for dedicated halls and buildings commonly run ten years or more, long enough to span several refresh cycles.

Giga Energy warns that leaving a colocation contract early or shrinking its footprint can cost the tenant money. Giga also says providers charge less per megawatt for a large, long commitment than for a small, flexible deployment.

Write these clauses into the lease as figures and dates:

  1. Initial term: a length set against the hardware refresh cycle, with each refresh inside the term counted and its power and connectivity changes written into the lease.
  2. Renewal: the notice that stops an automatic renewal and a cap on the renewal rate, since 3EX says auto-renewing contracts often renew at higher market rates.
  3. Termination and exit: the termination options, the notice each one requires and the exit penalty for each year of the term.
  4. Expansion rights: a right of first refusal on adjacent space, meaning the provider offers that space to the tenant first, with its kW limit and claim notice period.
  5. Contraction rights: the kW the tenant can release, the earliest release date and the penalty, priced before signature.
  6. Technology refresh clause: power and connectivity upgrades allowed mid-term without change-order fees or a term extension, at the interval the hardware refresh requires.
  7. Decommissioning: the process for removing hardware and the method for destroying data at the end of the term.

SLA credits and the gaps in an uptime percentage

A 99.9% uptime guarantee allows about 8.77 hours of downtime a year, and 99.999% allows about 5.26 minutes. Those figures cover outages on the facility's side of the division of work between a colocation data center and its tenant.

The calculation method sets what a written 99.9% is worth: whether scheduled maintenance counts against it, and whether the clock starts at the failure or at the ticket. 3EX suggests at least 48 to 72 hours of notice before scheduled maintenance.

3EX says SLA credits usually come as a percentage of the monthly recurring charge, rising in tiers with outage length. Some premium agreements pay 10 times the pro-rated value of the downtime.

Ask for eight terms in the SLA beyond the headline percentage:

  1. Uptime calculation: the formula, the start of the clock and the treatment of scheduled maintenance in the percentage.
  2. Credit tiers: the credit for each outage length, written into the SLA with its multiplier.
  3. Repair time: a promised time to repair next to the response time, because 3EX points out that a response time measures when a technician acknowledges the ticket.
  4. Cooling SLA: Introl lists supply water within 1°C of specification, a 15-minute response to cooling failures and penalties up to $10,000 per hour.
  5. Throttling penalties: penalties for temperature excursions that force GPUs to slow down to protect the chips, with the temperature thresholds stated in the SLA.
  6. Exclusions: force majeure (events outside either party's control), carrier failures and tenant-caused outages, each defined in the contract.
  7. Remote hands: the tasks covered, the billing basis and bundled monthly hours where offered, since 3EX says remote hands work is usually billed apart from the base charge.
  8. Audit right: access to real-time power and cooling data and the right to inspect the facility.

The tenant absorbs the compute lost on a throttled rack, so write exact cooling figures and penalties into the SLA. Racks such as the GB200 NVL72 depend on liquid cooling for AI hardware, which makes the cooling terms as important as uptime.

Which lease clause to push on first, by GPU rollout pattern

The clause to negotiate first depends on how the racks arrive.

Rollout patternClause to push firstReason
Delivery in batchesUtilization floor and its deadlineA floor that starts before racks arrive bills idle power
One delivery dateTerm length and renewal capCommitted and drawn kW match from the first day
Uncertain demandContraction rights and growth reservationBoth set the price of shrinking or growing at signing

A term sheet request covering the four terms needs seven items:

  1. Committed kW: per cabinet and summed across the lease, written into the Service Order.
  2. Utilization floor: its percentage and deadline, with the clock starting at each rack's switch-on date.
  3. Rack delivery dates: the delivery and switch-on dates, with a remedy for late facility power.
  4. Term and renewal: an initial term matched to the hardware refresh cycle, the renewal notice period and a cap on the renewal rate.
  5. Contraction and expansion rights: contraction with a stated penalty, and expansion rights on adjacent space.
  6. Cooling SLA: tolerance, response and penalty figures, next to the uptime percentage and its calculation method.
  7. Audit right: access to power and cooling data.

Send the request to the provider before lawyers start drafting the MSA, so each item enters the term sheet as a number.