AI Data Centers

Data Center Microgrids: Islanding, Control and Mixed On-Site Generation

A data center microgrid coordinates control of the data center's generation, storage, and loads, as well as its interaction with the utility grid. It can also island from the grid and operate independently.

Data center microgrids coordinate on-site generation, batteries, and utility power, as speakers at the Data Center World 2026 session "How to Use Complex Microgrids to Support the Data Center Power Strategy" explained. This requires more complex control systems, which operators may accept to bring behind-the-meter generation online before a new utility interconnection becomes available. Some data centers start with standby generators for backup power. Others pursue microgrids primarily to get power faster.

What Separates a Microgrid from Backup Generation?

Microgrid consultant Jim Reilly described a microgrid as an energy management system that operates across the point of interconnection between the facility and the utility grid.

Data centers may have diesel standby generators as part of their resilience architecture, but these alone do not make the facility a microgrid. A microgrid coordinates generation, storage, and loads, operating either autonomously or in conjunction with the grid.

IEEE Std 2030.7-2017, "Standard for the Specification of Microgrid Controllers," defines functional requirements for microgrid controllers, including those supporting grid-connected and islanded operation.

Why Use a Microgrid for Speed to Power?

Long interconnection queues are pushing data centers to consider on-site generation.

Michael Stadler, CTO of Xendee and a speaker at Data Center World, estimates that traditional utility interconnection can take 7 to 10 years in some markets, while behind-the-meter generation can bring a data center online in less than a year. These are his estimates, not guaranteed timelines for individual projects.

Cleanview found that interconnection queues for large loads can reach seven years in some US regions and that projects representing approximately 30% of planned US data center capacity intend to use behind-the-meter resources, according to Utility Dive.

By reducing the utility capacity required initially, microgrids can allow data centers to begin operations sooner.

What Does Islanding Require?

Islanding allows a data center to disconnect from the utility grid and use on-site generation and storage to supply selected loads.

Patrick Hughes of the National Electrical Manufacturers Association (NEMA) told Data Center World that utilities increasingly value data centers capable of disconnecting from the grid during peak demand. He believes demonstrating this flexibility can help data centers secure interconnection faster.

IEEE 2030.7-2017 addresses microgrid control functions for grid-connected and autonomous operation, including transitions between the two.

The data center must therefore define which loads will remain operational during islanding, which generation and storage resources will support them, and for how long.

What Must the Microgrid Controller Do?

The microgrid controller monitors generation, storage, and loads, coordinating available resources to meet the site's power requirements.

Bloom Energy, a fuel-cell generator vendor, explains that controllers monitor generators, inverters, batteries, and other resources to determine how on-site generation and grid power should be used. If available power cannot meet the data center's total demand, the controller can prioritize critical IT loads and reduce lower-priority loads.

IEEE Std 2030.7-2017 establishes the current functional requirements for microgrid controllers. A revision project, P2030.7, was authorized on March 27, 2025.

The National Rural Electric Cooperative Association (NRECA) says the proposed revision includes Annex E, "Data Center Energy Management Systems," addressing the control requirements of data centers operating under dynamic grid and load conditions.

IEEE 2030.7-2017 is scheduled to become inactive in December 2027 under IEEE's ten-year standards lifecycle unless the revision process supersedes it sooner.

For now, IEEE 2030.7-2017 remains the active standard, while P2030.7 is still under development.

How Can a Microgrid Use Mixed Generation Technologies?

Microgrids can combine different generation, storage, and cooling technologies to meet site-specific power requirements.

In May 2023, Vespene Energy and Viridi Energy announced a project at the Marathon County Landfill in Wisconsin. According to the EPA, the project was designed to convert landfill gas into electricity for on-site uses, including data processing, and generate revenue without a grid interconnection while a renewable natural gas facility was being developed.

At the time of the EPA's report, the landfill's reciprocating engines were being refurbished for on-site generation, while the data center was temporarily using grid power.

At a larger scale, Stadler discussed a proposed 16 MW university data center using gas generators, combined heat and power, absorption chillers, solar, batteries, and cold storage. The model projected annual energy costs below $20 million, compared with $32 million in the baseline case.

These examples highlight two different applications: monetizing an underused fuel source and optimizing the combination of generation, cooling, and storage at a larger facility.

How Do Data Centers Size Microgrid Battery Storage?

Battery storage requirements depend on the microgrid's objective, the loads it must support, and the required duration.

Stadler described two approaches:

  • Market participation: Some projects install gigawatt-hours (GWh) of battery energy capacity to support market participation, peak management, and grid services.
  • Backup and grid independence: Some designs provide enough energy to sustain selected loads for one to two days during extended grid outages.

These are examples rather than standard sizing requirements.

GWh measures the energy stored in the batteries, not how long they can operate. Storage duration depends on usable battery energy capacity and the power demanded by the supported loads.

What Regulatory Standards Apply to Data Center Microgrids?

The regulatory framework for data center microgrids is still developing.

NEMA has issued voluntary standards addressing energy storage systems and microgrids on data center campuses. Hughes noted that much of today's microgrid design process is proprietary, but greater standardization could improve safety and simplify engineering and utility reviews.

IEEE is also revising its microgrid controller standard to address newer distributed energy resource applications, including data centers.

For the bulk power system, FERC directed NERC to submit registry criteria and initial Reliability Standards for computational loads by December 31, 2026.

NERC's Large Loads Action Plan includes foundational standards addressing the reliability risks associated with large computational loads.

On October 26, 2026, NERC's Board of Trustees adopted its foundational computational-load Reliability Standards following their final ballot. The standards still require FERC approval before becoming enforceable in the United States.

NERC has also advanced registry criteria for computational load owners and operators. Their applicability and final requirements remain subject to the regulatory approval process.

Data center developers should monitor both the NERC requirements and the IEEE P2030.7 revision when designing microgrid controls and planning utility interconnections.

What Are the Best Practices for Designing a Data Center Microgrid?

Five decisions should guide the microgrid design:

  1. Identify the objectives. Determine whether the microgrid is intended for speed to power, resilience, grid independence, market participation, or a combination of these goals.
  1. Size generation and storage. Identify the loads to be supported, their power requirements, and the required operating duration. Use these requirements to determine generation capacity and battery storage needs.
  1. Define controller scope. Identify the generation and storage resources the microgrid controller will manage, along with any loads that can be reduced or shed during constrained operation.
  1. Establish islanding requirements. Coordinate with the utility to determine the required islanding and grid-support capabilities. Confirm that the microgrid has sufficient resources to sustain the selected loads independently.
  1. Follow applicable standards. Apply IEEE 2030.7-2017 where relevant and monitor the P2030.7 revision. Data centers potentially subject to NERC registration should also track the developing computational-load requirements and their applicability.